
Contractual and tort liability: the limits of the project owner's direct action in tort in the face of contractual prescription?
Published on :
16/01/2025
16
January
Jan
01
2025
While the project owner can sue builders under contract and, in the alternative, other parties in tort, he is prohibited from taking such action if he has allowed the limitation period applicable to contractual action to expire.
In the case brought before the Conseil d'État on 30 December, the Orne Chamber of Agriculture signed a public contract with a company to replace the windows in one of its buildings, which had subcontracted the carpentry to another company. In January 2010, the work was interrupted due to noise pollution caused by the newly installed windows. A bailiff's report in February confirmed these problems. After several years of inactivity, the Chamber of Agriculture appealed to the Caen Administrative Court in 2020 for compensation for various losses.
The Administrative Court of Appeal rejected its claims on the grounds that the contractual liability action against the company was time-barred. It also ruled that the Chamber could no longer take action against the subcontractor on the basis of tort, since it had allowed the limitation period applicable to the contractual action to elapse.
The Conseil d'État confirmed the analysis of the Administrative Court of Appeal, holding that the five-year limitation period had begun to run in February 2010, the date on which the damage was known with certainty. The action brought in 2020 was therefore out of time.
Décision n° 491818 - Conseil d'État
History
-
Confirmation of case law concerning work on existing structures: Installation of a wood-burning stove: no construction work, no ten-year guarantee
Published on : 11/02/2025 11 February Feb 02 2025PublicationsA couple had a house built and entrusted the structural work to a constructio...
-
Contractual and tort liability: the limits of the project owner's direct action in tort in the face of contractual prescription?
Published on : 16/01/2025 16 January Jan 01 2025ActualitésPublicationsWhile the project owner can sue builders under contract and, in the alternati...
-
Defective photovoltaic panels: what are the limits for warranties for companies in liquidation?
Published on : 07/01/2025 07 January Jan 01 2025ActualitésPublicationsThe question of insurance cover raises complex issues, particularly in terms...
-
Sub-contracting in maritime transport: quasi-delictual action excluded
Published on : 03/01/2025 03 January Jan 01 2025ActualitésPublicationsIn the field of maritime transport, Article L. 5422-19 of the French Transpor...
-
Defective health products: The nature of the causal link
Published on : 06/12/2024 06 December Dec 12 2024ActualitésPublicationsArticle 1245-8 of the French Civil Code provides that, in the field of extra-...
-
New article ‘High risks for German insurers in the event of direct action by France'
Published on : 23/05/2024 23 May May 05 2024PublicationsPublications / Florian ENDRÖSCommunicationWe are very pleased to present the new article ‘High risks for German insurer...